A step-by-step example video will be shown, focusing mainly on Clash Detective and TimeLiner.
For the planning, the estimated project execution tasks are as follows:
Phases | Taks | Duration (days) |
Foundation | 00_Excavation 01_Foundation 02_Wall_F 03_Columns_F | 5 6 7 4 |
Ground Floor | 05_Beams_GF y 06_Ceilings_GF 07_Columns_GF | 7 4 |
First Floor | 09_ Beams_FF y 10_ Ceilings_FF 11_Columns_FF | 7 4 |
Second Floor | 13_Beams_SF y 14_Ceilings_SF 15_Columns _SF | 7 4 |
Attic floor | 17_Beams_AF y 18_Ceilings_AF 19_Columns_AF | 7 3 |
Ceiling floor | 20_Beams_C y 21_Ceilings_C | 6 |
Stairs | 4_Stairs _F 08_Stairs_GF 12_Stairs_FF 16_ Stairs_SF | 3 3 3 3 |
* Working days from Monday to Friday.
** Holidays have not been considered.
*** Start expected on 01/01/2022